Colliers Way bridge rubble to be used to cover pipeline

December 13, 2013
By SHAE DALRYMPLE - Staff writer (sdalrymple@heraldstaronline.com) , Weirton Daily Times

WEIRTON The Weirton Sanitary Board voted Thursday to use remnants of the bridge at Colliers Way over U.S. Route 22 for filling in a hole which had been brought to their attention last month.

November's regular meeting ended with a resolution to spend up to $10,000 to cover a main pipeline exposed by landslides behind the Colliers Way Church of Christ, but now it seems some money can be saved on the project by reusing rubble from the bridge construction site nearby. Swank Construction has agreed to deliver the material to the church parking lot. This solution saves the sanitary board from purchasing about 3,000 tons of riprap (chunks of cement or rock) for the job.

"We finally caught a break on this one," Utilities Director A.D. "Butch" Mastrantoni said.

Article Photos

WATER LINE ON THE WAY — Equipment operators have been working on the ditch that runs along Freedom Way for about a month. Crews have placed more than 4,000 feet of pipe in the ground so far to replace Weirton’s main water distribution pipeline. The $6 million project is on schedule and set to reach Main Street in about two more weeks. “Everything’s going pretty smooth,” according to Ronnie Sheets, on-site inspector. Sheets updated the sanitary board on the progress at Thursday’s meeting. -- Shae Dalrymple

Members of the board also heard updates on the main distribution pipeline replacement from Wayne Morgan, who was standing in for Jonathan Carpenter of Thrasher Engineering, and Ronnie Sheets, on-site inspector. Sheets reported that most of the work at the waste water plant is completed, and the project is currently on schedule with approximately 4,000 feet of PVC pipe in the ground so far. Crews should be progressing to Main Street in about two weeks.

The board unanimously voted to approve an amendment to the contract for the distribution pipeline project allocating up to $35,000 for compaction and concrete testing fees. Because of heavy truck traffic, the West Virginia Department of Highways requested that testing be conducted on a daily basis. Mastrantoni is hopeful that the frequency of testing will be relaxed, in which case the full $35,000 would not be needed.

"The reason for not paying for it up front is that it's not always required," Morgan said. "There have been some savings in the original contract, so we're not projecting that the total project cost is going to go up. There are things going in the other direction off-setting this cost."

In other business, the board voted to purchase a replacement variable frequency drive for the rotary press at the treatment plant since the old one gave out last Friday. A VFD is designed to regulate the power going to pumps based on demand, which saves energy and makes operations more efficient. This piece of equipment will be purchased from Canada-based Fornier Industries at a cost of $3,850.

(Dalrymple can be contacted at sdalrymple@heraldstaronline.com)

 
 